SL. NO.
PROJECT TITLE
BRIEF DESCRIPTION OF PROJECT
VALUE (AED)
1
Roads for the Coastal area between Ras Ajeej and Taweela C # 2019
Abu Dhabi Municipality
Construction of Coastal Road 10 KM Access road 5 KM and Internal road network for the 200 houses at Al Bahya 14 KM and 100 houses at Al-Rahba 4 KM, Construction, Relocation and Protection of Services. (Irrigation7 KM, Sewerage 5 KM, 89 KM Electrical Cable works)
104,347,091
2
Construction & Maint. of Internal Roads for New houses in Ras Ajeej & Taweela, C #2019/1
Abu Dhabi Municipality
Construction of Coastal Road Access roads and Internal road network for the 192 houses at Al Rahba, Construction, Relocation and Protection of Services. (Storm Drainage 1 KM, 8 KM Irrigation lines, 12 KM Water Lines, Electrical 80 KM, Sewerage Works 1 KM)
60,388,900
3
Construction of Baniyas town roads sectors EB2/03,04 & EB2/01,02,03&04, C # 976/1
Abu Dhabi Municipality
Construction & Maint of roads and entrances to Villas, Construction, Relocation and Protection of Services. (Storm Drainage 1KM, Water 1 KM , 65 KM Electrical)
37,797,811
4
Al-Shamka Project -Third area Bridge Interchange, C # 974/1-5B
Abu Dhabi Municipality
Construction of Post-Tensioned Bridge 27m two spans dual carriageway, Carriageways & associated infrastructure
42,613,055
5
Construction of Internal Roads in Ras Ajeej area, C # 2019/3
Abu Dhabi Municipality
Construction & Maint of roads and entrances to 280 Villas. Construction, Relocation and Protection of Services. (3 KM Storm Drainage, 9 KM Irrigation, 87 KM Cable, 14 KM Water)
45,715,317
6
Roads & Interchange at Falah area Farms, C # 974/1/1/B
Abu Dhabi Municipality
Construction of Post-Tensioned Bridge 42m two spans dual carriageway, carriageways & associated infrastructure
62,469,647
7
Construction of Internal Roads in Shamka area, C # 974/2-3
Abu Dhabi Municipality
Construction of 47 KM single carriageway & 12KM of dual carriageway, Construction, Relocation and Protection of Services. (Storm Drainage 4 KM, Water 59 KM, Irrigation 15 KM, Electrical Cables 183 KM)
144,528,354
8
Construction Maint. & Rehab. works for & Minor projects for the Roads & Bridges of the emirate of Abu Dhabi (Western Region), C # 183/2004
Abu Dhabi Municipality
Construction/ Maint of Roads at various locations.
501,335,870
9
Paving the road between Arada & Al Burair Police Station in the western region
Abu Dhabi Municipality
Construction of 18 KM road 7.5m width & 2.5m wide outer shoulders with associated infrastructure works including Dune sand leveling 18 Million M³ and service works
38,154,327
10
Western Region Development Program - Zayed subdivision C # C200
CRD,
Emirate of AbuDhabi
Construction of 11 KM of roads, Sewerage works 11KM, Water works 14 KM, Irrigation works 9 KM, Electrical works 21 No of Sub Stations. Electrical Works 46 KM
53,111,611
11
Construction of Abu Dhabi International Shooting club C # 2000
Abu Dhabi Municipality
Construction of Earthworks, Pavement, Curbstone, Surface Drainage, Utility Works, Road Signs, Pavement Markings, Ducts etc;. Construction of Substations, Gate House, Garbage Depot & Ammunition Store.
92,007,164
12
Construction of Internal Roads in Khalifa City A, C # 972
Abu Dhabi Municipality
Construction of 50 KM single carriageway parking, Entrances, Footpaths & 2KM of Dual Carriageway Construction, Relocation and Protection of Services. (Storm Drainage 51 KM, Water 29 KM, Cable works 136 KM)
185,040,086
13
Roads for Mohammed Bin Zayed City (Fourth stage East) Sector Z-22,25,32 & 33, C #953/4-1
Abu Dhabi Municipality
Construction of 31 KM single carriageway & 8 KM Double carriageway & Parking, Entrances, Footpaths, Construction, Relocation and Protection of Services. (Storm Drainage 40 KM, Water 47 KM, Cable works 151 KM)
194,125,300
14
Completion, Maint., Improvement & Dualling of Al Madam Al Shweib Road
Ministry of Public Works
Construction of new Carriageway 20 KM and Rehab. of existing carriageway. Construction of 8 spans 30m Long Bridge with Precast beams. Construction, Relocation and Protection of Services for 20 KM length.
108,856,091
15
Maint., Rehab. & Additional works for Roads & Bridges in Abu Dhabi Emirate region(Western Region Highways & Bridges), C # 618/2006
Abu Dhabi Municipality
Construction/ Maint of Roads at various locations.
700,000,000
16
Infrastructure works for Public housing project, Al Salamt area Al Ain Phase 1, C # S100
CRD,
Emirate of AbuDhabi
Construction of 18 KM Roads & Parking, Entrances, footpaths. Construction, Relocation and Protection of Services. (Sewers 31 KM, Waterworks 18 KM, Cable works 171 KM, Irrigation 140 KM, Pumping station, Landscaping)
198,196,000
17
Roads for Mohammed Bin Zayed City Sector Z-34, C # 953/4-3
Abu Dhabi Municipality
31 KM single carriageway & 8 KM Double carriageway, Parking, entrances, Footpaths. Construction, Relocation and Protection of Services. (Storm Drainage 33 KM, Waterworks 24 KM, Cable works 59 KM)
116,836,000
18
Road from Madinat Zayed to Ghayathi, C # 5003
Abu Dhabi Municipality
Construction of Road 84 KM single Carriageway Construction, Relocation and Protection of Services. Dune sand leveling 18 Million M³. Chain link fencing 168 KM
450,340,000
19
Roads for the New Industrial area, South of the channel in Mussafah west, C # 992
Abu Dhabi Municipality
Construction of six lanes 7 KM road and two utility bridges of length 120m each, pipe culverts for 1200 - 1600mm Ø Pipes. Relocation of DI pipes 900-1200mm Ø.
221,344,000
20
Mafraq to Al Ghwaifat Border Post Highway Construction of the New Ruwais Bypass
Abu Dhabi Municipality
55 Km New Freeway (Ruwais Bypass), 12 km four lanes divided new link roads, 1 trumpet interchange, 4 dumbbell interchanges, 1 Bridge, 1 utility bridge, 6 underpasses, SW box culverts, etc. Relocation/ Protection of existing services, Electrical & Street Lighting works, Road marking & Road signs, Service works, etc.
2,895,761,728
21
Widening of Shk. Rashid Bin Saeed Al Maktoum St. from IP 40 to IP 49, C # 655
Abu Dhabi Municipality
Construction of the Additional lane & milling & overlaying of the full pavement width along both carriageways for an approximate length of 9 KM. Reconstruction of signalized intersections, taxi & bus lay bys, sidewalks, Street Lighting, Storm Drainage, Irrigation system, Traffic Control system, etc.
175,940,000
22
Maint. & Rehab. Works for Abu Dhabi Strategic Roads, Zone 1, Abu Dhabi Region, C #47/2008
Department of Transport
Construction/ Maint. of Roads at various locations.
120,000,000